30 July,2019 07:14 AM IST | Mumbai | Prajakta Kasale
The bridge that connects south Mumbai with the northern suburbs will be pulled down only after the construction of two parallel extended arms. Pic/Shadab Khan
The demolition and reconstruction of the Bandra-Dharavi bridge on the Mithi river will finally commence, as the BMC's seven-year-long wait to get all the necessary permissions, including crucial approval from the forest department, to go ahead with the project was received last week. Moreover, to ensure there is no traffic disruption or diversion, the bridge will be pulled down only after the construction of two parallel extended arms.
The 28-metre-wide bridge that runs by Dharavi and over the Mithi River is said to be a crucial link between south Mumbai and the northern suburbs. Civic officials said the bridge, said to be over 50 years old, was in bad shape due to wear and tear. "The reconstruction of the bridge was proposed in 2012. But due to litigation, the project never took off," said a senior civic official. With the disputes being finally resolved and the civic administration getting all the necessary approvals - from the environment clearance certificate for mangroves to other permissions from the forest department - the reconstruction is set to commence anytime soon.
Also Read: Mumbai: BMC takes up regular demolition action in Dharavi
Civic officials said the over 50-year-old bridge was in bad shape due to wear and tear
ALSO READ
Mumbai: Kurla residents to launch awareness drive during Ganpati
Dharavi NGOs support redevelopment survey, say opposition only by non-locals
NGOs in Dharavi support redevelopment survey, say opposition by non-locals
Dharavi health boost: SNEHA cuts malnutrition, ups awareness
This theatre production features young hip-hop artistes from Dharavi
A senior official from the bridges department said, "Around a year ago, a contractor was appointed for the job. We were just waiting for the clearance from the forest department. All the necessary approvals are in and now, all that is required is the BMC commissioner's orders to begin work on the bridge." He further said that while the department is prepared to start work, construction is usually not undertaken during the monsoon. "So it is just a matter of making the call on whether the work should commence immediately or after the monsoon," the official added.
To avoid any kind of traffic disruption or diversion, two parallel, extended arms will be constructed on either side of the bridge, each measuring eight metres in width. Once the reconstructed bridge is ready, the extended arms will be connected to it. As per the drawing board of BMC officials, the dimensions of the bridge would change upon its reconstruction. Currently, the bridge is 28 metres wide and 74 metres long. The new structure would be 44 metres wide and around 100 metres long. "The distance between the two pillars of the bridge will be such that it will not be an obstacle for the smooth flow of the river water," said engineers from the bridges department.
Also Read: BMC cracks down on illegal contractors, acts against four
2012
Year the reconstruction of the bridge was proposed
28m
Current width of the bridge
44m
Width after reconstruction
Graphic/Uday Mohite