03 September,2022 08:26 AM IST | Mumbai | Rajendra B. Aklekar
A man and machine rip up concrete chunks from Carnac Bunder bridge on Friday
The Central Railway on Friday started the demolition of the Carnac Bunder bridge. It is expected to take three months to completely pull down the structure. Railway officials said no train services would be hampered during the initial process of removal.
"Keeping in view the running of suburban trains, CR has decided to do the dismantling in available corridor margin during night time and also during Sunday mega blocks," Central Railway Chief Public Relations Officer Shivaji Sutar said.
Dismantling of Carnac Bunder bridge underway on Friday
"During these block margins, these works will be carried out: dismantling of parapet; dismantling of vertical columns along parapet; dismantling of concrete of corroded trough; and advance cutting prior to final removal, etc," he said.
ALSO READ
CR to run additional Ganapati festival special trains between Panvel and Madgaon
Ticket inspectors save passenger from coming under Mumbai-Kolhapur train
Mumbai locals are cheapest, speediest in world, says study
Central Railway to operate night block this weekend
Ganeshotsav 2024: CR to run 4 more services of unreserved Special Trains
Also Read: Mumbai: Carnac Bridge reconstruction hits another roadblock
After the initial phase, Sutar said, a mega block of about 30 hours will be implemented to remove the girder and complete the demolition. "The mega block is being planned in the third month of dismantling. During this block, the entire steel structure will be removed by using cranes."
After the over-150-year-old bridge was flagged as "dangerous" by IIT-Bombay in its audit a few years ago with recommendations of immediate closure as it had become a danger for the busy rail traffic passing below, the traffic police had put restrictions on heavy vehicular traffic on the bridge.
The bridge has important markings in Hindi, Gujarati and English with the letters 1868 and the name of the bridge carved on the plaques on all four sides. The railways has promised to save the plaques.
154