04 August,2023 02:02 PM IST | Mumbai | mid-day online correspondent
Photo/MMRDA
The Mumbai Metropolitan Region Development Authority (MMRDA) on Friday said that its experts have identified a total of 2783 potholes along ongoing projects, of which 2378 potholes have been successfully filled.
Out of the 1467 potholes found in the ongoing road projects, 1373 have already been addressed, MMRDA said in a statement. Similarly, of the 1316 potholes within the ongoing Metro projects, 1005 have already been filled. The remaining 425 potholes are set to be attended to within the next 48 hours, it said.
The statement said that MMRDA continues to demonstrate commitment to enhancing the city's infrastructure through its ongoing projects, ensuring a hassle-free monsoon experience.
Overcoming challenges:
ALSO READ
Ajit Pawar-led NCP to contest MLC election from Mumbai Teachers constituency
Shiv Sena's Shivaji Shendge to contest polls from Mumbai Teachers' constituency
Mid-Day Top News: Maharashtra assembly polls likely only after Diwali and more
Special | Maharashtra assembly elections: Who’s the real NCP in Mumbra-Kalwa?
Maharashtra assembly elections: Want unity, not CM post, says Uddhav Thackeray
Pothole repair involves navigating challenges like adverse weather conditions, heavy traffic, and the need for specific materials such as Mastic Asphalt, which requires high temperatures for bonding. Temporary measures like the cold mix, WMM (Wet Mix Macadam), DBM (Dense Bituminous Macadam), and Paver blocks are employed during heavy rainfall. Advanced techniques like mastic asphalt provide sustainable, long-term solutions.
Monsoon impact:
With Mumbai experiencing a record-breaking average rainfall of 2318.80 mm this Monsoon season, challenges have been substantial. July alone saw 1769.8 mm of rainfall (till July 31, 2023), surpassing the previous July record of 1502.6 mm in 2020. Despite such exceptional weather conditions, MMRDA remains steadfast in efficiently completing projects with minimal disruption.
Commitment to quality:
MMRDA maintains strict quality control even after project completion. Contractors are accountable for repairing road defects during the Defect Liability Period (DLP), ensuring road integrity even after transfer to relevant authorities.
Special planning authority's efforts:
MMRDA's Special Planning Authority extends its maintenance efforts to the Bandra Kurla Complex, Oshiwara District, and the Wadala Truck Terminal area. Here, approximately 28 km of concrete roads are diligently maintained. MMRDA's dedicated team tackles potholes and road issues with unwavering commitment, offering commuters a smooth driving experience.
Dr. Sanjay Mukherjee, IAS, Metropolitan Commissioner of MMRDA, reaffirmed his dedication to MMR's infrastructure development while prioritizing citizen convenience. Acknowledging the impact of heavy rainfall on waterlogging and pothole formation, he commended the fully equipped MMRDA team for their swift response and efficient coordination through the control room.