08 November,2022 08:05 AM IST | Mumbai | Rajendra B. Aklekar
The MRVC built the new staircase
Western Railway on Monday evening opened the new north-end staircase at Charni Road station in 28 days since they closed the old one. mid-day had been pursuing the issue diligently, highlighting the great inconvenience the closed staircase had caused local residents and regular commuters.
The Mumbai Railway Vikas Corporation's (MRVC) target for a linkway and the staircase was about 50 days.
Also read: Mumbai local train updates: No day block on Western Railway on November 6
ALSO READ
BMC completes transfer of girder from southern side of Gokhale Bridge
Mumbai rail upgrade: WR shifts another rail line to make way for sixth
Over Rs 62 crore collected as fines during ticket checking drives: WR
Mumbai: Second Gokhale bridge girder moves closer to completion
Mumbai: WR to operate 10-hour block between Goregaon, Kandivali this weekend
The Mumbai Railway Vikas Corporation announced on Sunday night that the staircase was complete and then it was opened on Monday evening. "Demolition of the old foot overbridge and building of a linkway and staircase for the new overbridge at Charni Road was completed by Team MRVC in 28 days, well before the target time of 45-50 days. For us passenger convenience is first and foremost," MRVC Chief Public Relations Officer Sunil Udasi said.
"We were given a target of 45-50 days, but we did it well before time, working day and night at the site. Within a period of 28 days, we managed to dismantle the old foot overbridge of two spans, the staircase, disposed of the dismantled material and constructed a linkway as well as a staircase," he added.
Charni Road station's island platforms 2 and 3 had been left without access at the Dadar-end due to the ongoing work. The only way to access the middle island platforms was via the Churchgate-end bridge which was very narrow and old. It had led to most commuters being forced to jump on tracks and trespassing, and Western Railway had to depute RPF personnel to discourage commuters from using the tracks.
"We are thankful to mid-day for keeping up the pressure on the authorities and getting the bridge staircase opened well within time. We are also thankful to the railway authorities for understanding the commuters' perspective and replacing the missing staircase within time," local resident and commuter Sadanand Beniwal said.
Rs 1.8cr
Total cost of work (including dismantling and reconstruction)
. Length of linkway: 20 metres
. Length of staircase: 25 metres
. Width of both: 3.25 metres
. Dismantling of old bridge: 40 metres x 4.5 metres
. Dismantling of staircase: 18X3 metres
. Total cost of work (dismantling and reconstruction): Rs 1.80 crore