05 May,2022 08:10 AM IST | Mumbai | A Correspondent
Once completed, these 7 STPs will recycle 2,464 MLD sewage every day for reuse
The plan to set up seven sewage treatment plants in the city is finally taking off with the Supreme Court appraising the tender process and directing the BMC to award contracts to the lowest bidders before May 31.
A BMC official said, "The court also directed that if any party or bidder has any objection to the tendering process, such objections shall be raised before the Supreme Court only. Such a direction was passed in a bid to obviate any further delay by the grant of stays or injunctions by any other court, thereby impeding the process of inviting bids for the setting up of STPs which are crucial to Mumbai."
The Brihanmumbai Municipal Corporation shortlisted contractors for the STPs at Worli (500 MLD), Bandra (360 (MLD), Malad (454 MLD), Ghatkopar (337 MLD), Dharavi (418 MLD), Bhandup (215 MLD) and Versova (180 MLD) at a cost of around Rs 26,000 crore, after the apex court directed the civic body to float and process tenders in February.
The civic body floated and processed the tenders between February and April and received three bids for Dharavi, three for Bandra, four for Versova, three for Ghatkopar, two for Worli, two for Malad and seven for Bhandup STP. In the hearing held on Wednesday, the court approved the process and set the next date of hearing in July to monitor the progress.
ALSO READ
Long queues at voting centres as first ever hawkers polls in city begin
Mumbai lakes providing drinking water reach 98.02 per cent capacity
Mumbai weather update: IMD forecasts moderate rainfall for the city
Ganesh Visarjan 2024: 62,569 Lord Ganesha idols immersed till 12 am, says BMC
Mumbai lakes supplying drinking water at 98.15 per cent capacity
Once completed, these 7 STPs will recycle 2,464 MLD sewage every day for reuse, which will in turn address the issue of environmental degradation.
July
Month when the SC will hear the matter next