13 July,2024 08:26 AM IST | Mumbai | A Correspondent
CD Barfiwala bridge connecting to Gokhale bridge in Andheri. Pic/Ashish Raje
A fact-finding committee has identified the misalignment between the Gopal Krishna Gokhale Bridge and the C.D. Barfiwala flyover in Andheri as a result of poor coordination between civic and railway officials. This oversight has caused embarrassment for the Brihanmumbai Municipal Corporation (BMC), which is now seeking an explanation from the concerned officers.
The BMC had established the committee to uncover lapses leading to such blunders. On Thursday, Additional Municipal Commissioner Dr Amit Saini submitted the report to the civic chief. While the committee did not recommend any disciplinary action, officials stated they would demand explanations from the responsible parties to prevent future errors.
According to the report, the new Gokhale Bridge is approximately 2.7 metres higher than the old C D Barfiwala connector, as it was constructed following new railway guidelines. After significant criticism, the BMC began alignment work on both structures on April 14. The work was overseen by experts from the Indian Institute of Technology-Bombay (IIT-B) and Veermata Jijabai Technological Institute (VJTI).
The alignment corrected the six-foot gap between the two structures, allowing the Barfiwala flyover to open to light motor vehicles last week. The C D Barfiwala connector crosses S.V. Road in Andheri West, providing signal-free movement for motorists from Juhu Gully and reducing bottlenecks near S V Road. The BMC spent around R8 crore on this alignment.
ALSO READ
Long queues at voting centres as first ever hawkers polls in city begin
Mumbai lakes providing drinking water reach 98.02 per cent capacity
Mumbai weather update: IMD forecasts moderate rainfall for the city
Ganesh Visarjan 2024: 62,569 Lord Ganesha idols immersed till 12 am, says BMC
Mumbai lakes supplying drinking water at 98.15 per cent capacity
Meanwhile, one arm of the Gokhale bridge was opened in February 2024, with the full bridge expected to be open for traffic by the end of the year. Currently, light motor vehicles are permitted to use the bridge.
2.7metres
Extent of the misalignment