11 November,2022 10:41 PM IST | Mumbai | PTI
File Photo
Western Railway will demolish the north-end carriageway of the Gokhale bridge over its tracks in Andheri before March 15 next year, while Mumbai's civic body will float tenders for reconstruction of the east-west connector on Saturday, officials said.
WR officials said the north-end carriageway will be demolished first and the south-end carriageway will be dismantled after the former is rebuilt.
The Brihanmumbai Municipal Corporation official said the tender for reconstruction will be for the entire structure, including the segment over WR's railway tracks, and the approach portions.
"Expert opinion will be sought on the stability of the bridge structure in the next eight days, and evaluation will be done to check if the south-end carriageway can be used for pedestrian movement and light vehicle traffic, including two and three-wheelers," the civic official said.
ALSO READ
Ajit Pawar-led NCP to contest MLC election from Mumbai Teachers constituency
Shiv Sena's Shivaji Shendge to contest polls from Mumbai Teachers' constituency
Mid-Day Top News: Maharashtra assembly polls likely only after Diwali and more
Special | Maharashtra assembly elections: Who’s the real NCP in Mumbra-Kalwa?
Maharashtra assembly elections: Want unity, not CM post, says Uddhav Thackeray
Also Read: Measles outbreak: High-level team to visit Govandi tomorrow
The decision was taken in a meeting of the BMC, WR and the metropolis' traffic police in the presence of Mumbai guardian minister Mangal Prabhat Lodha. he said.
Gokhale bridge has been shut for vehicular traffic from November 7 due to its dilapidated condition. The move has seen traffic bottlenecks in the area, officials admitted.
The reconstruction of the bridge will be done using precast material and the plan was to open at least one lane by June next year, they said.
"The plan is to demolish the bridge and keep precast material ready simultaneously for quick reconstruction. From March, the assembly of precast material will start. The road resurfacing of alternate roads, to be used during the closure of the structure, has been completed to give relief to motorists," the official informed.
This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever.