Home / Mumbai / Mumbai News / Article / Kurla station redevelopment delayed as only 40 percent of work completed

Kurla station redevelopment delayed as only 40 percent of work completed

The Kurla station upgrade under the Amrit Bharat Station Scheme has missed its deadline, with only 40 percent of the work completed. RTI activist Anil Galgali has raised concerns over the delay and called for action against contractors.

Listen to this article :
File Pic

File Pic

The redevelopment of Kurla Station under the Amrit Bharat Station Scheme is facing delays. The Central Railway administration has informed RTI activist Anil Galgali that the deadline of November 30, 2024, has already been missed, and only 40% of the work has been completed so far. He said this raises concerns among passengers about how many more months they will have to wait for the project’s completion.

In response to Anil Galgali’s RTI inquiry, the Central Railway revealed that a work order was issued to Technocrat Associates on December 7, 2023. The project was scheduled to be completed by November 30, 2024. However, due to the delay, passengers continue to face inconvenience. The railway administration stated that currently, only 40% of the work has been completed, with a total expenditure of ₹10.94 crore on the project.

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement