Home / Mumbai / Mumbai News / Article / Elphinstone bridge shut, crucial footbridge in limbo: Commuters fear tragedy

Elphinstone bridge shut, crucial footbridge in limbo: Commuters fear tragedy

With Elphinstone bridge finally shut and a crucial foot bridge next to it in limbo for the past six months, train commuters and residents of locality say they are staring at a possible tragedy

Listen to this article :
JCB machines begin demolition work on the Elphinstone bridge at around 10pm on Friday night. Pics/Ashish Raje

JCB machines begin demolition work on the Elphinstone bridge at around 10pm on Friday night. Pics/Ashish Raje

The Central Railway (CR) has failed to complete the much-awaited foot overbridge (FOB) parallel to the Elphinstone Road overbridge — a crucial link that would have allowed commuters and pedestrians to cross from east to west once the road bridge is shut for traffic.

The Western Railway (WR) side of the bridge, located in the west, was opened to the public a few years ago, followed by an extension across all WR lines. However, work on the CR portion, which began last year, remains incomplete. Because of this delay, the extended WR portion has also been rendered useless. At present, the bridge is used only as a passage to enter and exit Prabhadevi station and its WR platforms. The incomplete CR section is the only bridge directly parallel to the Elphinstone Road bridge, and could have offered major relief once the road bridge shuts.