Mumbai: Gokhale bridge contractor faces Rs 3.5-crore penalty
Updated On: 07 April, 2026 09:22 AM IST | Mumbai | Madhulika Ram Kavattur
The BMC has proposed a Rs 3.56 crore penalty on the contractor of the Gopal Krishna Gokhale Bridge project, while withholding Rs 7.78 crore from payments. The move follows delays and a major alignment flaw with the CD Barfiwala flyover

The part of Barfiwala bridge that connects to Gokhle bridge at Andheri West. FILE PIC/SHADAB KHAN
Following up on an RTI query which had revealed that the BMC had only levied a fine of Rs 5000, Advocate Godfrey Pimenta’s second RTI regarding the same matter, has now revealed that out of the Rs 87 crore contract cost of the whole project of the Gopal Krishna Gokhale Bridge, an amount of Rs 7.78 crore has been withheld by the civic body. The BMC claims that a fine of Rs 3.56 crore will be levied.
What happened
The Gokhale bridge’s completion had been delayed by two years due to a misalignment with the CD Barfiwala flyover, which left an almost 2-metre-wide horizontal and vertical gap between the bridges. This delayed the opening of the bridge to 2025. The bridge had been closed in 2022.