Updated On: 30 May, 2025 08:41 PM IST | Asif Ali Sayed
Maharashtra Deputy Chief Minister Eknath Shinde on Friday chaired a high-level meeting and told the Maharashtra State Road Development Corporation (MSRDC) officials to speed up road works across the state, an official statement said. Pics/Eknath Shinde`s office

1/6

2/6
Emphasising the importance of completing work on the Mumbai-Nashik highway before the monsoon, Shinde told the officials to ensure quality and timely completion of all projects
ADVERTISEMENT

3/6
During the review meeting, Eknath Shinde highlighted that 31 kilometres of concrete work on the Mumbai-Nashik highway remain unfinished. He called for urgent action to speed up work on stalled projects, including those at Pimpalasa Charoti and the railway overbridge, the statement said

4/6
Eknath Shinde also directed quick coordination with the railway authorities for megablock clearances to complete bridge work within a month
ADVERTISEMENT

5/6
Shinde stated that he expects the bridge on the Khadi near Kasheli to be finished by October and the one near Kalva by the end of June

6/6
Meanwhile, the Mumbai-Pune Expressway missing link work project was also discussed during the meeting and the work was expected to be completed by December, officials said