Updated On: 21 January, 2026 12:36 PM IST | ronak mastakar
Railway workers carry out maintenance work on the fast rail track between Borivali and Churchgate near Kandivali railway station on January 21, 2026. (Pics/Satej Shinde)

1/6

2/6
Meanwhile, Western Railway commissioned the sixth railway line between Kandivali and Borivali on Sunday evening, completing the long-awaited fifth and sixth lines between Bandra Terminus and Borivali
ADVERTISEMENT

3/6
The newly commissioned section is 3.210 km long and marks the completion of Phase One of the sixth line project between Bandra Terminus and Borivali

4/6
According to officials, a 30-day execution window was planned for the project, running from December 18, 2025, to January 17, 2026
ADVERTISEMENT

5/6
During this period, the existing fifth line between Kandivali and Goregaon remained suspended to facilitate the work

6/6
The commissioning involved extensive permanent way and structural engineering operations