The domestic airport flyover was opened with pompous arrangements and ribbon-cutting ceremony two days before the deadline on January 24.
The domestic airport flyover was opened with pompous arrangements and ribbon-cutting ceremony two days before the deadline on January 24.
u00a0
However, the first three lanes of the same flyover that wasu00a0 inaugurated six months back lies in improper state with uneven roads marring the entire stretch.
u00a0
Now, the Maharashtra State Roadu00a0 Development Corporation (MSRDC) has closed down this side of theu00a0 flyover between 12 midnight till 6 am for repair and leveling works.
u00a0
The vehicular traffic, which otherwise shouldnu00c3u00a2?Tt be affected once a flyover is opened for traffic, wouldnu00c3u00a2?Tt be able to drive for the nextu00a0 eight days.
An official from Public Works Department working at the spot said, "We had to open the other side of the flyover by January 24 and so could not complete the levelling on time."
u00a0
They have putu00a0 up barricades at the start of the flyover to prevent vehicles fromu00a0 entering at this stipulated time.
u00a0
Even MSRDC officials agreed that the pressure to complete the second portion of the flyover lead to this uneven road. Presently a layer ofu00a0mastic asphalt is being laid on the 20 metres stretch of the flyover.u00a0
ADVERTISEMENT
The Domestic Airport flyover is around 714 metres and has been built at a cost of Rs 34 crore.