Coastal road work delay to cost BMC an additional Rs 6 crore

The civic body will pay the extra amount to a consultant for a two-year extension of its contract

Listen to this article :
Workers seen at the construction site of the coastal road at Marine Lines, in May this year. File pic

Workers seen at the construction site of the coastal road at Marine Lines, in May this year. File pic

Further extension of the deadline for completion of the coastal road work is going to cost the Brihanmumbai Municipal Corporation (BMC) an additional Rs 6 crore. The civic body will pay the extra amount to the consultant for a two-year extension – one year of pre-consultation work and one year for construction activities. The work is already running behind schedule.

On January 23, 2017 M/s AECOM Asia Company Limited was appointed as the general consultant for the coastal road project. The BMC had decided on a 68-month time frame for completion of the project and Rs 34.92 crore was sanctioned as consultation fees. This included eight months of pre-consultation work, three years of construction activities and two years of defect liability period.