Once wires are fixed, trials on Dahisar-D N Nagar line will begin in March-April and the line could be ready to start by May

Work being done on the overhead equipment
In an important step towards completion of the Dahisar-D N Nagar Metro line 2A project, Mumbai Metropolitan Region Development Authority (MMRDA) has started work on the overhead equipment (OHE). MMRDA expects to start the trial run on the corridor by March-April this year.
Work on the OHE is one of the major milestones in the Metro Rail Project. The OHE mainly consists of the mast, cantilever, contact and catenary wires. The mast and cantilever have already been erected.