Karnak railway flyover’s 550-metric-ton girder successfully shifted

The 550-metric-ton northern girder of the Karnak Railway Flyover has been successfully shifted into place, marking a significant milestone in the reconstruction of the flyover connecting Masjid Bunder and P. D'Mello Road.

Listen to this article :
File Pic

File Pic

In a major milestone for the Karnak Railway Flyover project, the 550-metric-ton northern girder, an essential part of the flyover connecting the Masjid Bunder Railway Station with P. D'Mello Road, has been successfully shifted into place in the railway section.

The Central Railway administration carried out this complex operation between 01:30 and 04:00 on Friday, 31st January 2025, during a special block, which allowed for both traffic and power supply interruptions. The work was completed within a window of two and a half hours, marking a significant achievement.

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement