Updated On: 28 January, 2026 08:08 AM IST | Mumbai | Vinod Kumar Menon
Developers of stalled Neelkanth Kingdom project in Vidyavihar West given 60 days to get going with registration that will lead to key clearances, thanks to solicitor-resident Stuti Galiya fighting while 499 residents stay silent

The Neelkanth Kingdom complex on Nathani Road in Vidyavihar West. File pic/Shadab Khan
After a six-year legal battle, a single flat owner has secured a landmark ruling from the Maharashtra Real Estate Appellate Tribunal (MahaREAT), directing the developers of the stalled Neelkanth Kingdom project in Vidyavihar West to register the entire project under the Real Estate (Regulation and Development) Act, 2016 (RERA) within 60 days.
The order overturns a June 18, 2019, decision of the Maharashtra Real Estate Regulatory Authority (MahaRERA), which had held that only the project’s balance amenities required registration.