Updated On: 20 August, 2023 07:51 AM IST | Mumbai | A Correspondent
In a meticulously coordinated effort with the Monorail team, MMRDA team orchestrated a special engineering operation from midnight to 5 am, showcasing seamless coordination.

Pic/Sayyed Sameer Abedi
An important achievement occurred as MMRDA successfully placed two large U-girders, each spanning 27 meters and weighing 157 MT, above the operational Monorail at Chembur Nakka.
Tweeting about the same MMRDA said, “Another Milestone Conquered! Team Metro Line-2B has triumphed over challenges, achieving yet another incredible milestone. With unwavering determination, we successfully launched two massive U-girders (each spanning 27 metres and weighing 157 MT) over the operational Monorail Crossing P762-P763 at Chembur Nakka, VN Purav Marg, Chembur.” In a meticulously coordinated effort with the Monorail team, MMRDA team orchestrated a special engineering operation from midnight to 5 am, showcasing seamless coordination.