Bellasis flyover work ahead of schedule, set for Dec 2025 completion: BMC

Additional Municipal Commissioner (Projects) Abhijit Bangar stated that efforts are being made to complete the work by December 2025 so that the flyover can be opened for traffic earlier than expected

Listen to this article :
The construction of the historic Bellasis flyover underway. Pic/BMC

The construction of the historic Bellasis flyover underway. Pic/BMC

The reconstruction of the historic Bellasis flyover connecting Tardeo-Nagpada to Mumbai Central station is progressing rapidly. The project aims to be completed ahead of schedule, by 31 December 2025, instead of the originally planned April 2026, the BMC said on Monday.

The Mumbai civic body, in an official statement said that the flyover’s work within the railway limits is being carried out by Western Railway, while the Brihanmumbai Municipal Corporation (BMC) is constructing the approach roads.

In the first phase, the railway contractor has successfully installed 12 girders, each 36 metres long, as part of the major girder launching operation.