Home / Mumbai / Mumbai News / Article / High Court permits Metro III tunnel work under Fire Temples to continue

High Court permits Metro III tunnel work under Fire Temples to continue

Chief Justice Naresh Patil, permitted the work to continue at the Anjuman and Wadiaji Atash Behrams, adding that certain conditions must be followed

Listen to this article :
The Wadiaji Aatash Behram on Princess Street. Pic/Sameer Markande

The Wadiaji Aatash Behram on Princess Street. Pic/Sameer Markande

The much-anticipated judgment regarding the Metro tunnel work under Fire Temples did not pan out well for the Parsi community on Friday as The Bombay High Court gave the nod for the tunnel boring work as part of Metro III construction connecting Colaba-Bandra-SEEPZ.

Chief Justice Naresh Patil, permitted the work to continue at the Anjuman and Wadiaji Atash Behrams, adding that certain conditions must be followed. Among the conditions, Patil said that the team of experts constituted by the High Court would be present at the site, the equipment to monitor the structural stability will be installed permanently and continuous monitoring of the water level in the wells will be done.