Home / Mumbai / Mumbai News / Article / Mumbai: Himalaya Bridge to get an escalator in 5 months

Mumbai: Himalaya Bridge to get an escalator in 5 months

Approval for the bridge was given last week, installation to be completed by March 2024

Listen to this article :
The new escalator being installed at the bridge. Pic/Sameer Markande

The new escalator being installed at the bridge. Pic/Sameer Markande

The Brihanmumbai Municipal Corporation (BMC) has approved a proposal of Rs 1.29 crore to erect an escalator at the Himalaya foot overbridge (FOB) located opposite Chhatrapati Shivaji Maharaj Terminus. The escalator will be ready for use in five months. It has taken seven months for the civic body to pass the proposal after the bridge opened for pedestrians in March 2023.

According to BMC officials, the work order for the bridge was floated in May 2021, after the FOB collapsed on March 14, 2019. The original cost of the project was pegged at Rs 6.03 crore. According to the BMC document, while the work was ongoing, the railways suggested that the BMC install an escalator for the bridge.

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement