Home / Mumbai / Mumbai News / Article / Metro line connecting eastern and western suburbs completes 66 per cent work

Metro line connecting eastern and western suburbs completes 66 per cent work

The MMRDA further said that in addition to the 51.50 completion of work, the MMRDA has achieved 71 per cent via duct completion on the 15.31 km long Metro corridor of Metro line 6. Overall physical progress on this line is 66 per cent

Listen to this article :
Pic/MMRDA

Pic/MMRDA

The civil work on metro stations on line 6 is 51.50 percent complete, the Mumbai Metropolitan Region Development Authority (MMRDA) said in a statement on Monday. 

The MMRDA further said that in addition to the 51.50 completion of work, the MMRDA has achieved 71 per cent via duct completion on the 15.31 km long Metro corridor of Metro line 6. Overall physical progress on this line is 66 per cent.  

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement