Home / Mumbai / Mumbai News / Article / Mumbai Metro races against time to meet 2025 deadline

Mumbai Metro races against time to meet 2025 deadline

Four key corridors set to open this year, but delays and cost overruns continue; at least four Metro corridors have been targeted for completion by December 2025

Listen to this article :
Pic/Satej Shinde

Pic/Satej Shinde

The Mumbai Metropolitan Region Development Authority (MMRDA) is constructing an extensive Mumbai Metro network of 12 lines, spanning 337.1 km across the Mumbai Metropolitan Region (MMR). Of these, four lines covering 58.9 km (including the 12.44 km underground Aqua Line 3) are operational, while eight lines covering 165.7 km are at various stages of construction, with the remaining corridors still in the planning and tendering phase. At least four Metro corridors have been targeted for completion by December 2025.  

Mumbai Metro Network: Status update 

Yellow Line 2B 
Route: DN Nagar (Andheri) – Mandale (Mankhurd) 
Cost: Rs 10,986 crore 
Status: 83% complete; track work and finishing ongoing  

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement