Home / Mumbai / Mumbai News / Article / Mumbai: New steel deck gives boost to MTHL work

Mumbai: New steel deck gives boost to MTHL work

MMRDA recently launched 95 metre-long orthotropic steel deck

Listen to this article :
MMRDA orthotropic steel deck lifting work in progress for MTHL bridge

MMRDA orthotropic steel deck lifting work in progress for MTHL bridge

The MMRDA has sped up the work to complete the construction of Mumbai Trans Harbour Link (MTHL). A couple of days ago, it successfully launched a 95 metre-long orthotropic steel deck (OSD), weighing 920 metric tonnes.

This is the seventh successful launch of an OSD, a superstructure being used for the first time in the country, which will  carry the vehicular load more efficiently and improve the bridge’s load-carrying capacity. 