Updated On: 02 December, 2019 07:40 AM IST | Mumbai | Prajakta Kasale
A month after blaming CR for stalling project, BMC says 3-month hold-up caused because it's trying to save as many trees as possible

One of the 27 trees that needs to be uprooted for Hancock Bridge; (below) girders at the site. Pics/Ashish Raje
Even as the BMC last month blamed the Central Railway (CR) for the delay in the reconstruction of the vital Hancock Bridge connecting Mazgaon and Sandhurst Road, the contractor's letter seeking approval to cut down 27 trees for the project was stuck at the civic body's Garden Department.
mid-day had on November 6 reported that the Brihanmumbai Municipal Corporation accused the CR of seeking compensation at the end moment, delaying the work to restore the 140-year-old bridge demolished in January 2016. Later, the CR officials refuted the allegations saying, "There has been continuous progress from our side".