Rera tribunal tells builder to refund Rs 1 cr for late possession

The tribunal did not accept the builder's argument that buyers, by their action, had accepted the revised possession date and hence can seek no refund now

Listen to this article :
File photo of an under-construction building

File photo of an under-construction building

Stating that a builder cannot change the date of possession unilaterally, the Maharashtra Real Estate Regulatory Authority's (RERA) appellate tribunal directed a construction firm to refund around Rs 1.1 crore with interest to two persons who had withdrawn from a delayed project. As per the tribunal, the project was delayed by three years.

Also Read: Maharashtra RERA instructs builders to give back interest paid to 15 home-buyers