Updated On: 09 March, 2022 08:02 AM IST | Mumbai | Dharmendra Jore
State Load Despatch Centre asks Tata to explain non-compliance of its instructions twice last month

Workers at a medical shop check the stock manually, as their computer shut down because of power outage, at Walkeshwar, on February 27. Pic/Bipin Kokate
The Maharashtra State Load Despatch Centre (MSLDC), which manages the electricity network real-time, has served a notice to Tata Power Company Ltd, seeking explanation within 15 days for not following its instructions.
It has sought an explanation for “repeated non-compliance” of its control room instructions asking to pick up generation as per system requirement on February 27 when there was a 70-minute power outage in parts of the city and the suburbs, and on February 22 that threatened the electricity grid’s stability.