Updated On: 12 January, 2022 06:25 PM IST | Mumbai | Rajendra B. Aklekar
While the project is halted due to the Aarey car shed issue, so far MMRCL has managed to completed tasks worth Rs 5,000 crores. Read here for details

Representational Image. File Pic
Two trains for the controversial Mumbai Metro Line 3 are ready and a third will be ready soon said Ranjit Singh Deol, the managing director of MMRCL on Saturday. He added, with 15 per cent track laid, major developments expected this year.
While the project is halted due to the Aarey car shed issue, so far MMRCL has managed to completed tasks worth Rs 5,000 crores.