WR to operate 30-day block for 6th line work between Kandivali and Borivali
A major non-interlocking block will be undertaken for the commissioning of an electronic interlocking (EI) panel at Borivali on the UP and DOWN fast lines from 1 am to 7 am on December 27/28 (Saturday/Sunday). During the block, some UP Mail and Express trains will skip their halt at Borivali Station
Listen to this article :

Work underway to segregate express and local trains between Bandra and Borivali. File pic
Western Railway has announced a major 30-day block in connection with the construction of the 6th line between Kandivali and Borivali in Mumbai, from the night of December 20/21, 2025, and continuing until January 18, 2026.
Several suburban and long-distance trains will be affected during this period.