Updated On: 17 November, 2022 06:19 PM IST | Ahmedabad | PTI
The British-era suspension bridge on the Machchhu river in Morbi town collapsed on October 30, five days after it was reopened following renovation, killing 135 people

Morbi suspension bridge that had collapsed. File Pic/ PTI
The Morbi municipality has told the Gujarat High Court that the company tasked with renovating the bridge, which collapsed killing 135 people, reopened it without any prior approval and without informing the civic body about the repair work carried out.
In an affidavit submitted to the HC on Wednesday, the municipality also formed that condition 4 of the March 8, 2022 agreement (between the civic body and the company) said "it is for Ajanta (OREVA Group) to appropriately renovate and it is only thereafter that they would open it (the bridge) for the public at large, which would take minimum 8 to 12 months from the date of the agreement."