shot-button
Lake Levels Lake Levels
Home > Mumbai > Mumbai News > Article > Mumbai Repairs on Sion flyover set to begin by January 15

Mumbai: Repairs on Sion flyover set to begin by January 15

Updated on: 23 December,2019 07:07 AM IST  |  Mumbai
Ranjeet Jadhav | ranjeet.jadhav@mid-day.com

Commute towards South Mumbai to test commuters' patience as 1.1-km stretch to be shut for 45-day repairs

Mumbai: Repairs on Sion flyover set to begin by January 15

The MSRDC will change the load bearings and refurbish expansion joints of the flyover. Pics/Atul Kamble

The Maharashtra State Road Development Corporation (MSRDC) is set to shut the Sion Circle flyover for 45 days, making the commute to and from South Mumbai on the city's eastern flank more tedious. Motorists coming from and going to the Eastern Express Highway and Sion-Panvel Expressway will end up having to use the Dr Babasaheb Ambedkar Road on an already chaotic stretch.


Confirming the development, a senior MSRDC official said, "The bearings and jacks for the flyover's repair work have started arriving. The preliminary preparation work required before the actual repair has also begun. The repairs should begin sometime between January 10 and 15, 2020 and go on for 45 days. We are in touch with the traffic police, whose NOC will be needed before closing the bridge."


The load bearings and jacks, procured from Nashik and Hyderabad respectively, are currently being tested. The MSRDC will approach the traffic police with their plans in a couple of weeks. "We will have a presentation about the work, our plan of action and the time required. It will be shown to senior officials of the Mumbai Traffic police. They will work on the diversion plan, after which we will issue the notification for the flyover's closing," the official added.


The MSRDC will change the load bearings and refurbish expansion joints of the flyover

The repair work has been in the pipeline for over six months and was supposed to start in September. It was delayed as the required materials were still being manufactured. Currently, the 1135.30 metre (1.1 kilometre) flyover remains out of bounds for heavy vehicles. Its complete closure will probably lead to traffic chaos during peak hours, which in turn, will have a ripple effect on the Eastern Express Highway and Sion Panvel Expressway. However, one thing that motorists can be thankful for is the BKC-Chunnabhatti connector, which has absorbed a major chunk of the traffic.

The MSRDC will be changing the load bearings and refurbishing the expansion joints during the 45-day repairs. Earlier this year, heavy vehicles were banned from the flyover after a concrete portion from the outer side of the safety wall fell on the road below. The flyover has three lanes of which, one lane is dedicated for south-bound traffic and two are for north-bound traffic. A three-lane south-bound arm was going to be constructed but it did not materialise due to land acquisition problems.

Likely diversions
Motorists coming from South Mumbai and intending to take the Santacruz Chembur Link Road (SCLR) will likely be advised to use the Eastern Freeway to avoid traffic jams. Also, motorists going towards the western suburbs via the Dr Babasaheb Ambedkar Road will be requested to take the Sion-Dharavi Link Road.

1.1km
Length of the flyover

Catch up on all the latest Crime, National, International and Hatke news here. Also download the new mid-day Android and iOS apps to get latest updates

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!


Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK