Updated On: 01 February, 2025 07:30 AM IST | Mumbai | A Correspondent
Civic body completes girder launch, promises June 2025 opening; BMC had started shifting the 550-metric-ton girder earlier, but the process was halted on Sunday due to technical difficulties when only 12 metres remained

The girder placed over the railway tracks
The BMC completed the girder launching of Carnac Bridge early Friday morning. The bridge is expected to be completed before the monsoon. BMC had started shifting the 550-metric-ton girder earlier, but the process was halted on Sunday due to technical difficulties when only 12 metres remained.
During a special block taken by the Central Railway administration on Friday between 1.30 am and 4 am, railway traffic and power supply were temporarily suspended to facilitate the girder shifting. “The challenging task of shifting the 550-metric-ton northern girder of the Carnac Bridge, which connects P D’Mello Road near Masjid railway station, has been completed in the railway section,” said a BMC official.