shot-button
Ganesh Chaturthi Ganesh Chaturthi
Home > News > India News > Article > Airlines faced losses when MAFI project was underway

'Airlines faced losses when MAFI project was underway'

Updated on: 01 May,2014 06:27 AM IST  | 
Dheeraj Bengrut |

Flights of different airlines incurred losses during the Modernisation of Airfield Infrastructure (MAFI) project this year, which was underway from January 15 and April 15

'Airlines faced losses when MAFI project was underway'

Flights of different airlines incurred losses during the Modernisation of Airfield Infrastructure (MAFI) project this year, which was underway from January 15 and April 15.

Even though the MAFI project at Lohegaon, Pune, was completed in the stipulated time of three months, the airlines had to suffer several logistical setbacks, said Dhairyashil Vandekar, chairman of Pune Airlines Operators Committee.

Vandekar said, “A majority of the prime flights, of which there were 10 international and 15 domestic connecting flights, were affected. Airlines had to bear the cost of sending the flyers to Mumbai, so that their travel plans would not be affected.

Due to this, the airlines had to face losses to the tune of crores. Extra ground staff were deployed. The airlines had to rework the routes to maintain their slots. On a few occasions, airlines had to cancel their scheduled flights that originated from Pune.”

He added, “Air traffic control, Central Industrial Security Force, customs and immigration also coordinated with us.”




"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!


Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK